HomeMy WebLinkAbout10/19/2022 - Meeting Agenda
Advisory Board
Meeting
October 19, 2022
Pursuant to City Code 2.14.060(A) and Utah Code section 52-4-207(2), the Airport
Advisory Board adopted a rule permitting electronic meetings for this Board, regardless
of whether a quorum is present at an anchor location, so long as such meetings comply
with the Open and Public Meetings Act.
To access the meeting please visit:
https://saltlakecity.webex.com/saltlakecity/onstage/g.php?MTID=e3a8e6f412e4a6932a43b82
93aaaa2ca4
ADVISORY BOARD MEETING AGENDA
19 October 2022
9:00 A.M.
CONSENT
A. Minutes of the 21 September 2022 Meeting
DISCUSSION
A. Director’s Report – Bill Wyatt, Executive Director, SLCDA
B. Airport Redevelopment Program (ARP) Update – Brian Stetson, Deputy
Program Director, SLCDA
C. Review of Financial Position– Brian Butler, CFO, SLCDA
D. Master Plan- Brady Fredrickson, Director of Planning and Environmental,
SLCDA
MEDIA CLIPPINGS
Media Clippings – October 2022
INFORMATION ITEMS
Financial Report- August 2022
Air Traffic Statistics – August 2022
Construction Report –October 2022
The next meeting will be held on Wednesday, November 16, 2022, at 9:00 a.m.
Meetings are usually held in the Board Room, located on the third level of the airport
terminal and via Web-ex unless otherwise posted. People with disabilities may make
requests for reasonable accommodations no later than 48 hours in advance in order to
attend this Airport Advisory Board Meeting. Accommodations may include alternate
formats, interpreters, and other auxiliary aids. This is an accessible facility. For questions
or additional information, please contact Brett Christensen at 801-575-2042.
Advisory Board
Meeting
October 19, 2022
Agenda
Advisory Board
Meeting
September 21, 2022
Minutes
SALT LAKE CITY DEPARTMENT OF AIRPORTS
MINUTES OF ADVISORY BOARD MEETING
September 21, 2022
Members Present: Steve Price, Chair
Theresa Foxley
John Bradshaw
Karen Mayne*
Dirk Burton
Roger Boyer*
Mayor’s Office Rachel Otto*
City Council Sam Owen*
Victoria Petro-Eschler
Department of Airports: Bill Wyatt, Executive Director
Brett Christensen, Executive Assistant
Treber Anderson, Director of Operations
Eddie Clayson, Director of Maintenance
Medardo Gomez, ORAT Director
Brady Fredrickson, Director of Planning and Environmental
Pete Higgins, Chief Operations Officer
Mike Williams, ARP Program Director
Nancy Volmer, Communication and Marketing Director
Melyssa Trnavskis, Director of Design and Construction Mgmt.
Ed Cherry, Director of IT*
Brian Butler, Chief Financial Officer*
Shane Andreasen, Director of Admin. and Commercial Services*
Megan DePaulis, Senior City Attorney*
Catherine Brabson. City Attorney*
Stefhan Bennett, SLC Police Captain*
Brady George, Battalion Chief*
Nate Lavin, Airport Service Development Manager
Other:
Kory Cox, HOR Inc.
Steve Price called the meeting, held in-person at the SLCDA Admin Offices Board Room and
via Webex, to order at 9:11 a.m. (* indicates the party attended virtually)
AGENDA
A. Minutes
A motion was made by Steve Price to approve the minutes of August 3, 2022, as presented. All
votes were affirmative; motion passed.
B. Director’s Report
Bill Wyatt, Executive Director, updated the Airport Advisory Board regarding current events,
growth of the Airport, gate allocation, and the AUA. Also speaking briefly on wheelchair
accessibility.
Mayor Burton asked how a person interested in pushing a wheelchair would go about applying
for that job. Wyatt explained that applications can be filled out at
https://www.prospectair.com/employment/ there is also a link on the Airport website.
Theresa Foxley asked if the criminal background checks are required through TSA. Wyatt
explained that yes, everyone that goes to the secure side of the airport without a ticket must have
a badge or be escorted by someone with a badge.
Foxley inquired about wheelchairs and if there are self-guiding mobility options. Wyatt spoke
about new wheelchairs we are receiving at the airport.
Steve Price gave praise for the AUA in combination with a 10-year lease extension. Wyatt
replied with acknowledging the whole team for working so hard on the agreements.
C. Airport Redevelopment Program (ARP) Update – Mike Williams, ARP Director,
SLCDA
Mike Williams, Airport Redevelopment Program (ARP) Director, presented an update on the
ARP (presentation on file). Main points included were:
• Safety and Schedule Stats, and Cost Summary
• Near Term Schedule Milestones
• ARP Overall Budget
• Concourse ‘A’ East/Central Tunnel/Airfield
• Concourse ‘B’ East
• Overall Phase 2 and Phase 3 Phased Delivery
• Job progress photos
• New TSA exit doors
Burton asked if there are sensors on the security doors. Mike Williams explained there are
multiple sensors, cameras and three compartments you walk through. If you decide to turn
around once you’re inside the doors, alarms will go off.
Tye Hoffman inquired about the hardstand and when we will no longer be using them. Wyatt
explained the hard stand we are using right now for Delta will go away in the fall of 2023.
Concourse B will likely have a permanent hardstand hold room for low-cost carriers that have a
need for it.
D. Phase IV Overview & Gate Review – Shane Andreasen, Director of Airport
Administration/Commercial Services, SLCDA
Shane Andresen, Director of Airport Administration/Commercial Services, presented an update
on the Phase IV, Main points included were:
• Summary of gates
• Level 1 Program
o Support space for airlines and concessions
• Final Gate Layout
• Level 1 Hardstand & Employee Bus Plaza
• Level 2 & 3 Program
o Center far east end will be two escalators to take people downstairs to 7 gates
o 15,000 SF Third-Party Lounge
• Final Gate Layout
o Mid concourse tunnel will stay open
o From 2023-2027 we will be opening gates each year
Hoffman asked about needing additional gates for international travel. Wyatt explained we have
six international gates right now. We are in a good space having a sterile corridor and doubling
the size of the Federal inspection station.
E. AUA Amendment- Brian Butler, Chief Financial Advisor, SLCDA
Brian Butler, Chief Financial Advisor, presented an update on the AUA, Main points included
were:
• Affordability Analysis
o Days Of Cash on Hand
o Debt Service Coverage
o Airline Cost per EP
• Financial Projections – Phase IV
• AUA Amendment Highlights
o Net Terminal Revenue Requirement
o Increased Revenue Sharing
o Terms
o General Language
• Next Steps
o Air Carrier Briefings
o Updated Phase IV Estimate & Design
o City Council Budget Amendment Approval
There were no further questions.
Steve Price adjourned the meeting at 10:24 a.m.
___________________________ ________________________
Steve Price, Chair Date
___________________________ _________________________
Erin Mendenhall, Mayor Date
Advisory Board
Meeting
October 19, 2022
Discussion Items
AGENDA: DISCUSSION ITEM (A)
DATE: 19 October 2022
TO: Airport Advisory Board
FROM: Bill Wyatt, Executive Director
SUBJECT: Executive Director’s Report
Bill Wyatt, Executive Director, will present a monthly informational report to the
Board, which may include:
1. ARP progress
2. Ground transportation update
3. Concessions and rental cars
4. Airport safety and security
5. Airport facilities and operations
6. General aviation
7. Passenger and airport users
8. Environmental matters
9. Financial condition
10. Legislative issues
11. Airlines
12. Communications and marketing
AGENDA: DISCUSSION ITEM (B)
DATE: 19 October 2022
TO: Airport Advisory Board
FROM: Bill Wyatt, Executive Director
SUBJECT: Airport Redevelopment Program Update
Brian Stetson, Airport Redevelopment Program (ARP) Deputy Program Director, will
present an update on the SLC Airport Redevelopment Program (presentation on file).
Status Update 10/19/2022
AIRPORT REDEVELOPMENT PROGRAM
Safety, Statistics and Schedule
Safety Statistics
Numbers for September
–OSHA National Average
–Lost Time Rate 1.60 Recordable Rate 2.50
–HDJV Metrics
–9,737,602 Total Trade Hours worked
–Lost Time Rate 0.22 Recordable Rate 2.30
Trade Hours for the Program Overall
–ARP Metrics (HDJV+AOJV)
–11,899,217 Total Trade Hours worked
Trade Workers on Site
–790 Trade Workers (week ending 10/07/2022)
Schedule Status -Critical Path
–Airfield -Completion of Airfield Paving and Activation of Taxilane 2E (North)
–SCE –Completion of Hydro-Piping Flush and Fill
–SCE –Start-up of Air Handler Units & Conditioning of Air
–NCP Phase 3 –Completion of Structural Steel Erection and Placement of Elevated Deck Concrete
–Overall Program is on schedule
2
Near Term Schedule Milestones
3
Airport Redevelopment Program Overall Budget
4
Construction Budget
September 2022
Budget
9/22/22 FOC
Committed
Aug-22
Commitments
Sep-22
*Pending
Commitments
Revised
Commitments
Earned
to Date
Estimate at
Completion
Closed TRP CGMPs 1, 2, 2A-2D, 3, 4, 5, 7, 9, 09A, 12 $1,532,021,660 $1,532,021,660 $0 $0 $1,532,021,660 $1,532,021,660 $1,532,021,660
Closed NCP CGMPs 13, 14, 15, 16, 17, 18 & 19 $487,852,444 $487,852,444 $0 $0 $487,852,444 $487,852,444 $487,852,444
CGMP 2E,F&H CMAR General Conditions/Services $107,642,170 $100,410,170 $0 $0 $100,410,170 $35,995,000 $107,642,170
CGMP 06 Parking Garage, Roadways, CUP $403,477,666 $405,856,439 $0 ($2,378,773)$403,477,666 $401,115,592 $403,477,666
CGMP 10 South Concourse East/Tunnel Shell $554,410,047 $554,410,047 $0 $0 $554,410,047 $379,458,852 $554,410,047
CGMP 11, 11A & 11B Apron Paving & Fueling $275,423,126 $203,341,893 $0 $0 $203,341,893 $139,494,524 $275,423,126
CGMP 19A Phase 3 NCP/Tunnel Buildout $332,870,248 $332,870,248 $0 $0 $332,870,248 $58,605,692 $332,870,248
CGMP 20 NCP Phase 2 Airfield Paving & Jet Fuel $77,645,774 $77,645,774 $0 $0 $77,645,774 $6,661,082 $77,645,774
Total Program Construction $3,771,343,135 $3,694,408,675 $0 ($2,378,773)$3,692,029,902 $3,041,204,846 $3,771,343,135
TRP Owner Procurement $5,472,527 $5,472,527 $0 $0 $5,472,527 $4,808,421 $5,472,527
NCP Owner Procurement $3,039,266 $3,039,266 $0 $0 $3,039,266 $1,860,182 $3,039,266
Security Checkpoint Equipment $12,506,042 $11,751,472 $0 $0 $11,751,472 $7,848,061 $12,506,042
Automated Security Exit Door Equipment $917,430 $917,430 $0 $0 $917,430 $0 $917,430
TRP Soft Cost $383,005,010 $326,373,020 $3,756,000 $0 $330,129,020 $301,306,308 $383,005,010
NCP Soft Cost $185,593,794 $139,639,623 $0 $0 $139,639,623 $110,699,387 $185,593,794
Total Program Soft Cost $590,534,069 $487,193,338 $3,756,000 $0 $490,949,338 $426,522,359 $590,534,069
CGMP 2G CMAR Preconstruction Phase 4 $1,414,757 $1,414,757 $0 $0 $1,414,757 $1,222,353 $1,414,757
NCP Soft Cost Phase 4 $16,547,016 $16,539,531 $0 $0 $16,539,531 $10,431,312 $16,547,016
Total Phase 4 Planning Cost $17,961,773 $17,954,288 $0 $0 $17,954,288 $11,653,665 $17,961,773
TRP Owner Reserve $22,057,342 $0 $0 $0 $0 $0 $22,057,342
NCP Owner Reserve $50,076,743 $0 $0 $0 $0 $0 $50,076,743
Total Program Owner Reserve $72,134,085 $0 $0 $0 $0 $0 $72,134,085
Total ARP Program Budget $4,451,973,062 $4,199,556,301 $3,756,000 ($2,378,773)$4,200,933,528 $3,479,380,870 $4,451,973,062
*Pending Commitment for Final/Closeout Revision to CGMP 6 will reduce the CGMP 6 commitment to the 09/02/21 Budget
Airport Redevelopment Program Overall Phase 4 Adjusted Budget
5
Concourse ‘A’ East/ Central Tunnel/Airfield
Central Tunnel
•Moving Walkway Installation Progressing
•Mechanical, Electrical and Plumbing Installation Progressing
•Fire Protection Installation Progressing
•South and North Access Hole Concrete Infill Complete
•Wall and Soffit Drywall Studs Underway
Concourse ‘A’ East
•Mechanical, Electrical and Plumbing Rough-in Progressing
•BHS Early Bag Storage Conveyor Installation Progressing
•IT/Special Systems Cabinet/Cabling Installation Progressing
•Ceiling Grid and Column Cover Installation Continuing
•Terrazzo Installation in Main Circulation Areas Progressing
•Restroom Fixture, Millwork, Toilet Partitions and Mirror Installation Progressing
•Started Concrete Floor Pre for Carpet
•Started Holdroom Gate Signage
•Started Passenger Boarding Bridge Installation 6
Concourse ‘A’ East/ Central Tunnel/Airfield
Airfield
•Site Utilities Progressing
•Hydrant Fuel System Flushing of Loop around Concourse ‘A’
East Complete
•Airfield Paving East/West Taxilane Production Paving
Progressing
•Airfield Paving South and North Sides of Concourse ‘A’
Progressing
•Airfield Paving Over Central Tunnel –Main Area Complete
•Taxiway ‘H’ for Rehabilitation Activities Progressing
7
Concourse ‘B’ East (Phase 3)
Concourse ‘B’ East 8 Gate (Phase 3)
•Foundation Formwork and Concrete Placement Progressing
•Building Shallow Underground MEP Progressing
•Slab-on-Grade Concrete Placement Continuing
•Structural Steel Erection Progressing
•Started Elevated Metal Deck Installation
8
9
Overall Phase 2 and Phase 3 Phased Delivery
High Speed BHS Conveyor
Operational May 2024
Baggage Make-up
Operational May 2024
Open Gate B24 May 2024
Phase 4 –Gate Delivery Schedule
10
11
Closing up South Central Tunnel Access
12
Airfield Activities
Passenger Boarding Bridge Installation Passenger Boarding Bridge Installation
Paving Taxilane 2E Paving Taxilane 2E Looking East
13
Concourse A East –Level 1 Interior Progress
Back of House Restroom Progress
Level 1 Permanent Power Back of House Corridor Diamond Plate
Concourse ‘A’ BHS Early Bag Storage
14
Concourse A East –Level 2 Interior Progress
Early Gate Separation Wall Framing
Concession Space Area A Looking East from Area E to Far East End
Wall Framing Far East End
15
Central Tunnel–Interior Progress
High Speed Baggage Cell –BHS/Ductwork
Main Passenger Walkway Studs Moving Walk Installation
Drywall and Ductwork Progress
16
Concourse B (Phase 3)
North Ductbank
Phase 3 Steel Erection Phase 3 Steel Erection
Additional Sky Club Expansion Foundations
AGENDA: DISCUSSION ITEM (C)
DATE: 19 October 2022
TO: Airport Advisory Board
FROM: Bill Wyatt, Executive Director
SUBJECT: Review of Financial Position
Brian Butler, Chief Financial Officer, will present an update on the Financial Audit.
1
Salt Lake City Department of Airports
Review of Financial Positionas of June 30, 2022
Presentation to Airport Advisory Board
October 19, 2022
2
FY 2022 Financial & Operational Highlights
Passenger traffic increased 66% over FY 2021
Landed weights increased 14.3% over FY 2021
Operating revenue increased 40.2% over FY 2021
Operating expenses under budget by 13.1%
Terminal Redevelopment Program (TRP) and North Concourse
Program (NCP) spent to date $3.4 B
3
Enplaned Passenger Traffic
Annual Enplanements
Actual
2018
Actual
2019
Actual
2020
Actual
2021
Actual
2022
Budget
2023
Enplanements (000s)12,420 13,090 10,096 7,710 12,802 13,933
Annual Change 4.8%5.4%(22.9%)(23.6%)66.0%8.8%
6
8
10
12
14
16
20
1
4
20
1
5
20
1
6
20
1
7
20
1
8
20
1
9
20
2
0
20
2
1
20
2
2
20
2
3
Mi
l
l
i
o
n
s
Enplanements
Enplanements
4
CPE Ten Year History -SLC
$3.84 $3.90 $3.65 $3.69 $3.53 $3.83 $3.90
$5.41
$11.25
$8.11
$2.50
$3.00
$3.50
$4.00
$4.50
$5.00
$5.50
$6.00
$6.50
$7.00
$7.50
$8.00
$8.50
$9.00
$9.50
$10.00
$10.50
$11.00
$11.50
$12.00
FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22
5
Budget Comparison
Description FY 2022
Budget FY 2022 Actual Favorable /
(Unfavorable)
Operating Revenue $249,663,000 $ 258,945,000 $ 9,282,000
Airline Revenue Sharing (2,376,000)(13,566,000)(11,190,000)
Operating Expense (161,864,000)(140,619,000)21,245,000
Net Operating Income $ 87,799,000 $ 118,326,000 $ 30,527,000
Source: Salt Lake City Department of Airports.
6
Dash Cash on Hand
Fund Balance as of 6/30/2020
(in millions)
Balance as of 6/30/2021 (in
millions)
Balance as of 6/30/2022
(in millions)
Unrestricted
Surplus Fund *$397 $125 $164
Revenue Fund *3 15 15
Restricted
PFC Fund 13 3 3
CFC Fund 3 0 1
Debt Service Reserve and
Capitalized Interest Funds 220 223 412
Other Restricted Funds *28 32 373
Total $664 $398 $968
Funds Available for Operations*$428 $172 $199
Days cash on hand 1,433 424 515
Source: Salt Lake City Department of Airports.
*Funds available for operations include Surplus Fund, Revenue Fund, Operating and Maintenance Reserve Fund and Renewal and Replacement Fund
7
Airline Use Agreement Rates and Charges
FY22 Due or (Owe) Calculation Amount
LANDING FEES
Due $40,173,300
Less Net Billed (46,503,700)
Net Owed to Airlines $(6,330,400)
TERMINAL RENTS
Due $ 76,600,600
Less Net Billed (68,699,100)
Net Owed to Airlines $7,901,500
Net Owed from Airlines for the FY22 Reconciliation $1,571,100*
* Amount owed from Airlines will be rolled forward into the FY24 rates.
8
Comparison of Actual Airline Revenue
Revenue Category FY 2020 Actual FY 2021 Actual FY 2022 Actual
Landing Fees $ 35,638,000 $ 35,995,600 $ 45,157,900
Terminal Rents 36,081,700 65,985,000 83,479,900
Airline Revenue Sharing (10,096,900)(7,710,200)(13,566,000)
Support Buildings 4,421,400 4,454,200 4,346,400
Passenger Boarding Bridge 1,913,100 1,572,300 1,630,700
Fuel Farm 538,800 1,169,900 1,804,400
Remain overnight 157,800 511,100
TOTAL AIRLINE REVENUE:$ 68,653,900 $ 101,977,900 $ 123,253,000
Source: Salt Lake City Department of Airports.
9
Airline revenues represent a modest but increasing share of total
operating revenues
Source: Salt Lake City Department of Airports.
$57,565 $61,560 $68,654
$101,978
$123,253
$165,548 $181,504
$161,326
$184,684
$258,945
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
2018 2019 2020 2021 2022
Fiscal Year
2018 2019 2020 2021 2022
Airline Share of
Total Revenue 34.8%33.9%42.6%55.2%47.6%