HomeMy WebLinkAboutCouncil Provided Information - 1/13/2026NET MAINTENANCE 2025
Roadway Construction Projects
Presented by Jorge Chamorro , Public Services Department Director &
Julie Crookston, Public Services Deputy Director
SALT LAKE CITY
Background
•New designs
•Inventory increasing
•One year warranty expiring
Methodology
•Programs/types of assets
•Concrete, traffic signals, signs, markings (paint),
surface treatments, sweeping, and snow removal
•Net change
•Maintenance costs and labor hours
•Key:
•Caveats
Net Decrease Net Increase
300 W Protected Bikeway
Map of
Projects
KEY
Traffic signs/signals
Livable Streets area
City road
SALT LAKE CITY
Asset Summary
Asset Type Count Net Change Unit
Curb & Gutter 33,289.73 ft
Flatwork (and Waterway)104,400.01 sq ft
Stamped Concrete/Pavers 68,763.99 sq ft
Detection Systems 23 ea.
High-intensity Activated Crosswalk 4 ea.
Accessible Pedestrian Signal Buttons 116 ea.
Rectangular Rapid Flashing Beacon 17 ea.
Signs & Support 935 ea.
Delineators 339 ea.
Yellow Lines 9,958 ft
White Lines 28,235 ft
Crosswalks 1,876 ft
Green/Red MMA 43,078 sq ft
Bike Symbols 192 ea.
Other Symbols 116 ea.
Bars, Crosshatching, etc. 13,358 ft
Asphalt Roadway (5.19)lane miles
Protected Bike Lane 34.21 miles
2100 S
SALT LAKE CITY
Summary
Total Net Change
Maintenance Cost Labor Hours Labor Cost
$120,971.12 4,197.43 ~3 FTEs $159,830.38
1100 E
•Total construction costs for these projects were
$111,900,000
•Maintenance/labor costs represent 0.25% of total project
funding and ~2% increase to Streets budget.
Thank you!
Jorge Chamorro, Public Services Director – jorge.chamorro@slc.gov
Julie Crookston, Public Services Deputy Director – julie.crookston@slc.gov
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $27,476.23 92.44 $4,137.29
Traffic Signals $14,237.16 17.03 $623.41
Signs $131.56 0.52 $226.30
Markings (Paint)$25,560.19 53.97 $2,190.92
Surface Treatments $(4,924.82)79.81 $3,652.95
Sweeping - 3.69 $170.35
Snow Removal $24.71 126.64 $123.55
Project Total $62,505.03 374.10 $11,124.76
SALT LAKE CITY
200 South
From 400 W to 900 E
Funded with 2018 FOF Bond; completed in phases 2022 -2024
BEFORE
AFTER
SALT LAKE CITY
300 North
From 300 W to 1000 W
Funded with 2018 FOF Bond Class C Fund FY23, CIP FY23; completed
2025
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $1,698.15 1.45 $80.52
Traffic Signals $8,339.27 29.02 $1,181.43
Signs $87.68 16.48 $955.62
Markings (Paint)$5,917.23 31.61 $1,349.59
Surface Treatments $(3,085.80)260.63 $11,928.82
Sweeping - 3.01 $139.19
Snow Removal $20.19 103.48 $100.95
Project Total $12,976.72 445.68 $15,736.12
AFTER
SALT LAKE CITY
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $1,735.56 7.89 $370.20
Traffic Signals -0.00 -
Signs $257.04 15.86 $893.42
Markings (Paint)$7,337.30 18.68 $982.21
Surface Treatments $(1,801.61)495.12 $22,661.53
Sweeping -3.67 $169.77
Snow Removal $24.63 126.21 $123.13
Project Total $7,552.92 667.43 $25,200.26
300 W Protected Bikeway
From 900 S to 400 S
Funded by State Transportation Grant 2023; completed 2025
AFTER
SALT LAKE CITY
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $491.42 3.78 $173.12
Traffic Signals $300.64 7.28 $291.36
Signs $127.76 16.40 $969.08
Markings (Paint)$823.98 12.10 $547.17
Surface Treatments - 225.00 $10,298.25
Sweeping - 0.00 -
Snow Removal - 0.00 -
Project Total $1,743.80 264.55 $12,278.98
400 S Bus Islands
From Redwood Rd. to 900 W
Funded by CDBG, CIP FY22; completed 2023
AFTER
AFTER
SALT LAKE CITY
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $1,562.51 4.07 $185.40
Traffic Signals -0.00 -
Signs $105.32 9.88 $587.84
Markings (Paint)$56.40 2.97 $135.76
Surface Treatments $(1,402.64)55.06 $2,519.96
Sweeping -0.00 -
Snow Removal -0.00 -
Project Total $321.59 71.98 $3,428.96
700 S 1000 W Roundabout
Funded by CIP FY23 Constituent Request and 2018 FOF Bond;
completed 2025
BEFORE
AFTER
SALT LAKE CITY
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $9,497.23 -25.64 $(1,133.74)
Traffic Signals $11,867.05 5.55 $166.16
Signs $338.36 51.38 $3,055.08
Markings (Paint)$(137.89)3.78 $513.14
Surface Treatments $(69,196.82)-868.86 $(39,767.57)
Sweeping - 8.82 $407.68
Snow Removal $59.14 303.07 $295.68
Project Total $(47,572.93)-521.90 $(36,463.57)
900 South
From 900 W to Lincoln St. (950 E)
Funded by County Active Transportation Grant, RDA funds, PU
funds, and 2018 FOF Bond; completed 2023/2024
BEFORE
AFTER
SALT LAKE CITY
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $1,072.20 4.80 $219.77
Traffic Signals $4,784.67 26.23 $1,042.26
Signs $64.18 8.98 $538.39
Markings (Paint)$2,862.18 18.62 $750.82
Surface Treatments $(1,901.35)87.63 $4,010.95
Sweeping -2.36 $109.20
Snow Removal $15.84 81.18 $79.20
Project Total $6,897.72 229.80 $6,750.59
1100 East
From 900 S to Logan Ave.
Funded by 2018 FOF Bond; completed 2024
AFTER
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $9,636.92 22.67 $1,009.77
Traffic Signals $2,165.35 0.0015 $0.06
Signs $92.60 14.22 $904.61
Markings (Paint)$177.93 29.20 $1,156.16
Surface Treatments $(3,319.58)119.80 $5,483.31
Sweeping -0.00 -
Snow Removal -0.00 -
Project Total $8,753.22 185.89 $8,553.91
SALT LAKE CITY
2100 South
From 700 E to 1300 E
Funded by 2018 FOF Bond, PU funds, CIP FY23; completed 2025
AFTER
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $1,056.79 0.70 $34.60
Traffic Signals -0.00 -
Signs $33.88 4.24 $247.82
Markings (Paint)$464.02 3.89 $219.10
Surface Treatments $(1,090.94)62.82 $2,875.37
Sweeping -0.00 -
Snow Removal -0.00 -
Project Total $463.75 71.65 $3,376.89
SALT LAKE CITY
500 N 1000 W Intersection
Funded by CIP FY21; completed 2025
AFTER
DURING
AFTER
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $1,593.95 -76.83 $(3,261.59)
Traffic Signals $1,601.16 0.99 $29.40
Signs $(37.41)2.16 $158.54
Markings (Paint)$2,366.15 3.96 $134.67
Surface Treatments -180.00 $8,238.60
Sweeping -0.00 -
Snow Removal -0.00 -
Project Total $5,523.85 110.28 $5,299.62
SALT LAKE CITY
Highland Dr.
From Ramona Ave. to Driggs Ave.
Funded by 2018 FOF Bond and State Grant; completed 2024
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $2,159.51 36.07 $1,562.41
Traffic Signals -0.00 -
Signs $35.41 3.32 $201.16
Markings (Paint)$684.70 20.45 $711.37
Surface Treatments -540.00 $24,715.80
Sweeping -0.00 -
Snow Removal -0.00 -
Project Total $2,879.62 599.84 $27,190.74
SALT LAKE CITY
Virginia St.
From South Temple to 11 th Ave
Funded by 2018 FOF Bond; completed 2024
BEFORE
AFTER
BEFORE
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $2,088.79 8.02 $366.76
Traffic Signals $9,031.05 16.72 $575.25
Signs $69.93 6.90 $422.49
Markings (Paint)$1,139.10 14.59 $410.70
Surface Treatments $(3,210.48)257.52 $11,786.66
Sweeping - 0.00 -
Snow Removal - 0.00 -
Project Total $9,118.39 303.74 $13,561.86
AFTER
SALT LAKE CITY
West Temple
From 400 S to North Temple
Funded by 2018 FOF Bond and UDOT’s Transportation Investment
Fund; completed 2024
BEFORE
AFTER
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Concrete $6,709.65 12.03 $547.80
Traffic Signals $67.23 1.74 $67.71
Signs $416.09 27.82 $1,626.06
Markings (Paint)$1,475.00 35.34 $1,377.34
Surface Treatments $(3,584.52)1305.70 $59,761.94
Sweeping -0.00 -
Snow Removal -0.00 -
Project Total $5,083.45 1382.63 $63,380.85
SALT LAKE CITY
Livable Streets
Various locations in Zones 2, 3, 4
Funded by CIP FY23; completed 2025
Net Change
Program/Asset Type Maintenance
Cost Labor Hours Labor Cost
Traffic Signals $44,724.00 11.75 $410.42
Project Total $44,724.00 11.75 $410.42
SALT LAKE CITY
Traffic Signals
Various locations
Funded by CIP, state grants, and federal funds; completed 2024/25
CITY COUNCIL OF SALT LAKE CITY
451 SOUTH STATE STREET, ROOM 304
P.O. BOX 145476, SALT LAKE CITY, UTAH 84114-5476
SLCCOUNCIL.COM
TEL 801-535-7600 FAX 801-535-7651
COUNCIL STAFF REPORT
CITY COUNCIL of SALT LAKE CITY
TO:City Council Members
FROM: Kate Werrett
Budget & Policy Analyst
DATE:January 13, 2026
RE:2025 Roadway Construction Net Maintenance
ISSUE AT-A-GLANCE
Public Services submitted an update on the 2025 roadway construction projects and the associated ongoing
maintenance costs.
Goal of the briefing: Receive details regarding 2025 roadway construction projects and their estimated
impact on annual roadway maintenance. As part of the FY2027 proposed budget, these additional
maintenance costs will be considered by the Council.
ADDITIONAL & BACKGROUND INFORMATION
Public Services has provided an update on Salt Lake City’s roadway inventory after the completion of several
projects during 2025. Included in this update is the anticipated impact of the improvements on annual
maintenance costs. Additional details can be found beginning on page 7 of the administrative transmittal.
Due to the addition of more livable street elements and other more variable roadway elements, Public Services
intends to provide annual updates on newly constructed roadway assets. These presentations will include:
1. Ongoing roadway inventory maintenance cost changes by asset type
2. Estimated net change in annual roadway maintenance costs
3. Estimated net change in roadway maintenance labor hours and labor costs
The construction costs for these projects totaled approximately $111.9 million. With the increase in roadway
inventory assets, Public Services expects annual maintenance costs to increase by approximately $280,000. This
is a 2% increase to the Street Division budget. The Street Division is reviewing options to absorb some of the
additional costs and anticipates asking for additional ongoing funding in the FY2027 budget.
Policy Topics:
- The Council may wish to discuss the maintenance impacts on the FY2027 annual budget.
- The Council may wish to discuss with the Administration how recent legislation may impact decisions on
future investments.
ATTACHMENTS
1)Administrative Transmittal: 2025 Roadway Construction Net Maintenance